 The next phase, Phase 5, of the renovation of Jefferson Avenue downtown will begin on Tuesday.

The contractor on Tuesday will begin removing pavement on Jefferson between the CN Railroad crossing and Banker Street, including the Front Street intersection. The removal on Front Street will extend approximately 15 feet north and south of the existing crosswalks.

Front Street between Washington Avenue and St. Anthony Avenue will remain open.

Sidewalks will remain open utilizing temporary ramps and crosswalks.

Meanwhile, the contractor is wrapping up work on Phase 4, from 3rd Street to 4th Street. It's anticipated Phase 4 will be open to traffic in the afternoon on Wednesday, September 25.